PROJECTS · SAN GABRIEL, CALIFORNIA
Mission Sierra
Developed and built by RCG. Three three-storey residences built from the ground up in San Gabriel, replacing a single 1,660 SF home — Spanish-inspired architecture with rooftop decks and modern interiors.
Project Overview
Mission Sierra replaces a single 1,660 SF home with three three-storey residences on the same parcel. The design takes its cues from San Gabriel’s Spanish architecture and pairs them with open modern floor plans, private rooftop decks and a separate entry and garage for each home.
RCG led the development as well as the construction. We found the property, took it through the City of San Gabriel permitting process and secured the construction financing.
On the build side, we carried the project from a cleared lot through foundations, framing, the exterior envelope, underground electrical and permanent power, driveways and flatwork, and interior finishes, delivering three finished homes on a single site.
LOCATION
San Gabriel, California
Los Angeles County
SCOPE
Development + ground-up build
Site acquisition, permitting, construction financing and construction of three residences replacing one 1,660 SF home.
STATUS
Complete
All three residences finished, from exterior and flatwork through interior finishes.
Where the Project Stands
From finding the property to three finished homes. Here is the project phase by phase.
01 · Site Acquisition
Complete — We found the property, a single 1,660 SF home in San Gabriel, and acquired it for redevelopment.
02 · Design and Permitting
Complete — We took the project through the City of San Gabriel plan check and permitting process.
03 · Construction Financing
Complete — We secured the construction financing that funded the build.
04 · Demolition and Grading
Complete — The original residence was removed and the lot cleared and graded, with three building pads set out across the parcel.
05 · Footings and Slabs
Complete — Footings formed, reinforced and inspected, then poured across all three residences ahead of vertical construction.
06 · Sewer and Plumbing Rough-In
Complete — New sewer and below-slab plumbing installed and tied in before the slabs were closed.
07 · Three-Storey Framing
Complete — Each residence framed to three storeys, with floor and roof decks sheathed and braced ready for the building envelope.
08 · Envelope and Stucco
Complete — Windows set, exterior sheathed and stucco applied, with roof deck railings and exterior trim detailed.
09 · Underground Electrical and Permanent Power
Complete — With the buildings nearly finished, the utility trench was dug, underground electrical conduit set, and permanent power pulled and energised at the street.
10 · Driveways and Flatwork
Complete — Driveway, walkways and patios formed, reinforced, poured and finished, giving each residence its own approach.
11 · Interior Finishes
Complete — Drywall, tile, cabinetry, plumbing fixtures and interior trim finished throughout all three homes.
12 · Final Inspections and Occupancy
Complete — Final inspections passed and all three residences completed.
Architectural rendering of the three Mission Sierra residences
The original parcel from the street, before demolition
Demolition of the existing single-family home underway
Excavator clearing the last of the original structure
Grading the lot with a loader
Lot cleared and graded, ready for building pads
Footing forms and rebar run along the property line
Plumbing risers stubbed up inside the slab forms
Rebar and forms set for the foundation slab
Reinforcement in place and ready for the pour
Foundation slab poured and finished
Steel moment frame lifted into place
Steel moment frame set and sill plates down on the slab
Wall framing begins on the slabs
First-floor framing laid out along the property line
Reviewing the plan set on site during framing
Second-floor framing up on the first residence
Three-storey framing sheathed, with scaffolding up
Electrical rough-in made up in a junction box
Electrical panel roughed in with home runs
Panel rough-in ready for inspection
Sheathed framing wrapped, with scaffolding going up
Framing wrapped and stucco materials staged on site
Three-storey framing wrapped, with scaffolding up
Scaffolding and lath going up for stucco
Scaffolding up for the stucco base coat
Stucco finish coat going on, with scaffolding still up
Clay roof tile loaded onto the roof
Clay roof tile going on from the scaffolding
Windows set and stucco nearly complete as scaffolding comes down
Brick veneer and stucco detailed at the base of the building
Exterior stucco complete with scaffolding removed
Drywall delivered to the framed upper floor
Drywall hung and taped, ready for finishing
Drywall taped and finished in an upper-floor bedroom
Drywall finished, with floors protected
Interior hallway primed, with doors hung
Open living area painted, with floors protected
Upper-floor room prepped for flooring
Kitchen cabinetry in place, ready for countertops
Kitchen cabinets and island installed
Team reviewing layouts on site in a finished garage
Quartz being custom cut on site
Kitchen countertop and undermount sink installed
Shower walls being tiled, with a niche framed in
Tiled shower wall with valve and head rough-in set
Shower tile complete, with a recessed niche
Tile stair treads installed
Shower glass installer on site
Finished bathroom with freestanding tub and tiled walls
Electrical panel trimmed out and labelled
Utility trench dug for the underground electrical service, with the buildings nearly finished
Underground electrical conduit set in the utility trench
Underground electrical conduit run below grade to the new service
Underground electrical conduit and grounding at the building wall
Conduit staged in the trench along the property line
Electrical conduit trench at the meter location
New copper water service stubbed up at the building
Sewer lateral and cleanout installed and connected
Residences complete outside, with the site cleared for flatwork
Exterior finishing work from scaffolding along the side yard
Storm drainage system installed below grade
Skid steer delivered for site grading
Equipment arriving for site work
Rough grade between the residences ahead of the driveway
Rough grading along the side yard
Side yard graded, with irrigation lines laid out
Old driveway approach removed for the new street improvements
Curb and gutter formed along the street frontage
Concrete walkway and curb poured alongside the residences
Driveway reinforcement laid between the residences
Driveway forms and rebar set at the rear of the site
Rebar grid set and tied for the driveway
Rebar grid checked for level before the driveway pour
Checking slope on the driveway reinforcement
Driveway slab poured and finished
Solar panels installed on the roof deck
Paver patio laid at the rear of the residences
Side walkway poured, with new landscaping along the property line
Side yard finished with the retaining wall and new planting
The finished front of Mission Sierra from the street
Aerial view of the finished building from the street
Side elevation with the garage and new landscaping
Second-floor balcony overlooking the street
The finished kitchen with island seating
Living room with street-facing windows
Open great room from kitchen to dining
Overhead view of the three finished residences and shared drive

