PROJECTS · SAN GABRIEL, CALIFORNIA

Mission Sierra

Developed and built by RCG. Three three-storey residences built from the ground up in San Gabriel, replacing a single 1,660 SF home — Spanish-inspired architecture with rooftop decks and modern interiors.

Project Overview

Mission Sierra replaces a single 1,660 SF home with three three-storey residences on the same parcel. The design takes its cues from San Gabriel’s Spanish architecture and pairs them with open modern floor plans, private rooftop decks and a separate entry and garage for each home.

RCG led the development as well as the construction. We found the property, took it through the City of San Gabriel permitting process and secured the construction financing.

On the build side, we carried the project from a cleared lot through foundations, framing, the exterior envelope, underground electrical and permanent power, driveways and flatwork, and interior finishes, delivering three finished homes on a single site.

LOCATION

San Gabriel, California

Los Angeles County

SCOPE

Development + ground-up build

Site acquisition, permitting, construction financing and construction of three residences replacing one 1,660 SF home.

STATUS

Complete

All three residences finished, from exterior and flatwork through interior finishes.

Where the Project Stands

From finding the property to three finished homes. Here is the project phase by phase.

01 · Site Acquisition

Complete — We found the property, a single 1,660 SF home in San Gabriel, and acquired it for redevelopment.

02 · Design and Permitting

Complete — We took the project through the City of San Gabriel plan check and permitting process.

03 · Construction Financing

Complete — We secured the construction financing that funded the build.

04 · Demolition and Grading

Complete — The original residence was removed and the lot cleared and graded, with three building pads set out across the parcel.

05 · Footings and Slabs

Complete — Footings formed, reinforced and inspected, then poured across all three residences ahead of vertical construction.

06 · Sewer and Plumbing Rough-In

Complete — New sewer and below-slab plumbing installed and tied in before the slabs were closed.

07 · Three-Storey Framing

Complete — Each residence framed to three storeys, with floor and roof decks sheathed and braced ready for the building envelope.

08 · Envelope and Stucco

Complete — Windows set, exterior sheathed and stucco applied, with roof deck railings and exterior trim detailed.

09 · Underground Electrical and Permanent Power

Complete — With the buildings nearly finished, the utility trench was dug, underground electrical conduit set, and permanent power pulled and energised at the street.

10 · Driveways and Flatwork

Complete — Driveway, walkways and patios formed, reinforced, poured and finished, giving each residence its own approach.

11 · Interior Finishes

Complete — Drywall, tile, cabinetry, plumbing fixtures and interior trim finished throughout all three homes.

12 · Final Inspections and Occupancy

Complete — Final inspections passed and all three residences completed.