Two state laws let developers build housing on land zoned for offices, retail and parking, in many cases without a rezoning, a hearing or CEQA review. Here is what qualifies and what it costs to use them.
Southern California has no shortage of underused commercial land: half-empty strip centers, aging office parks and surface parking lots along wide boulevards. Until recently, putting housing on those sites meant a general plan amendment, a rezoning and years of discretionary review.
AB 2011 and SB 6, both signed in September 2022 and effective July 1, 2023, changed that. They allow residential development on commercially zoned sites, and AB 2011 adds a ministerial, CEQA-exempt approval path. A 2024 amendment, AB 2243, expanded where the laws apply. AB 2011 is scheduled to remain in effect until January 1, 2033.
Two Laws, Two Different Tools
What it does: AB 2011: Creates a ministerial, CEQA-exempt approval path; SB 6: Makes housing an allowable use; no new approval process
Eligible zoning: AB 2011: Zones where office, retail or parking is a principally permitted use; SB 6: Office and retail commercial zones
Project type: AB 2011: 100% affordable, or mixed-income on a commercial corridor; SB 6: Residential, or mixed-use at least 50% residential
Affordability: AB 2011: Required (see below); SB 6: None beyond local inclusionary rules, unless SB 35 is used
Labor: AB 2011: Prevailing wage; more for larger projects; SB 6: Prevailing wage and skilled-and-trained workforce
Approval path: AB 2011: Ministerial, with set review deadlines; SB 6: Local process, or SB 35 streamlining where it applies
AB 2011: Ministerial Housing on Commercial Sites
Two pathways
100% affordable: every unit, excluding managers’ units, is affordable to lower-income households.
Mixed-income: the site must front a commercial corridor, generally a non-freeway street with a right-of-way of 70 to 150 feet, with at least 50 feet of frontage. AB 2243 reduced the minimum right-of-way to 50 feet for sites where local zoning allows heights of 65 feet or more.
Affordability for mixed-income projects
Rental: either 8% very low-income and 5% extremely low-income units, or 15% lower-income units.
For-sale: either 30% moderate-income units, or 15% lower-income units.
Affordable units must be distributed through the project and match the market-rate units in bedroom mix and quality. If a local inclusionary ordinance requires more, the local rule controls.
Density and height
In metropolitan jurisdictions, mixed-income projects receive the greater of local zoning or a state baseline that rises with site size, corridor width and transit proximity, from 30 units per acre on sites under one acre up to 80 units per acre within a half mile of a major transit stop. Height follows the same logic: the greater of local zoning or 35 feet, 45 feet or 65 feet depending on corridor width and transit. After AB 2243, projects must reach at least 75% of the applicable density, and state density bonus incentives do not trigger discretionary review. Cities cannot require parking, apart from bicycle, EV and accessible spaces.
Review deadlines
Cities must flag any inconsistency with objective standards in writing or the project is deemed consistent. Once consistent, approval must follow within 60 days for projects under 150 units and 90 days for larger projects.
SB 6: Housing as an Allowed Use
SB 6 is simpler. It makes housing an allowable use on office and retail sites of 20 acres or less, for residential projects or mixed-use projects at least half residential. It creates no new approval process, but a qualifying project can use SB 35 streamlining and the protections of the Housing Accountability Act. Commercial tenants on the site must receive notice and, where required, relocation assistance.
Labor Standards: Price Them In
Both laws carry labor requirements that belong in the pro forma from the first draft:
AB 2011: prevailing wage on all projects. Projects with 50 or more units must also provide apprenticeship participation and health care expenditures. The developer certifies compliance and submits monthly reports, with penalties for missing them.
SB 6: prevailing wage plus a skilled-and-trained workforce requirement, subject to a bidding exception, with per-worker daily penalties for violations.
These requirements raise construction cost compared with a conventional market-rate project. On many sites, the time saved by skipping a rezoning still makes the math work, but the comparison has to be run before you commit.
Sites That Do Not Qualify
Sites outside an urbanized area, or not substantially surrounded by urban development
Very high fire hazard severity zones and other environmentally constrained sites
Sites that would demolish rent-controlled, deed-restricted or recently tenant-occupied housing, or historic structures
Mobilehome and RV park sites
AB 2243 relaxed several original exclusions. Housing within 500 feet of a freeway can now qualify with air filtration, intake and balcony design measures, and the blanket industrial-adjacency exclusion was narrowed. It also opened regional mall sites of up to 100 acres, with block-size, open-space and frontage requirements.
How to Evaluate a Commercial Site
Confirm zoning and corridor width. Check the principally permitted uses and measure the right-of-way.
Screen the exclusions. Fire zones, environmental conditions, existing housing and historic resources can end the analysis early.
Choose the pathway. Compare AB 2011 mixed-income, AB 2011 100% affordable, SB 6 with SB 35, and a conventional entitlement.
Price labor and affordability. Build prevailing wage and the affordable unit mix into the construction budget and revenue model.
Check utility capacity. Commercial sites rarely have the electrical service, water and sewer capacity a residential building needs.
Planning a development?
Ramos Construction Group is a majority women-owned general contractor and developer based in Santa Ana. We run site and zoning feasibility, compare entitlement pathways, price labor requirements into lender-ready construction budgets, and coordinate utilities with SCE and municipal providers.
Call (949) 688-3455, text (949) 394-4753 or visit rcgbuild.com to schedule a feasibility consultation.
Sources
ABAG, AB 2011 and SB 6 Summary of Key Details: https://www.abag.ca.gov/sites/default/files/documents/2025-04/AB-2011-SB-6-Summary-Key-Details-4-2025.pdf
California HCD, Affordable Housing and High Road Jobs Act (AB 2011): https://www.hcd.ca.gov/sites/default/files/docs/planning-and-community/aff-hsg-high-roads-jobs-act-ab-2011.pdf
Burke, Williams & Sorensen, AB 2243: Expanding Housing Development Projects: https://www.bwslaw.com/?p=11002
This article is general information, not legal, financial or investment advice. Zoning, entitlement and permitting requirements vary by jurisdiction and change over time; confirm requirements for your site with the local planning and building departments.