A developer’s due-diligence checklist: what to verify about zoning, utilities, fees and exit value before the deposit goes hard.
A development deal is won or lost at acquisition. Once you close, the land basis is fixed, the carrying costs start and every surprise comes out of your margin. The due-diligence period is the one window where a problem costs you nothing but time to walk away.
Most buyers check price, title and the zoning map. The issues that sink projects usually sit elsewhere: utility capacity, offsite improvements, fees and site conditions that never show up on a listing. Here is the checklist we use before we recommend a site, whether for our own projects or for a client.
The Checklist at a Glance
Zoning and density: What to verify: Base zoning, general plan, overlays, state density programs; Why it matters: Sets how many units you can build
Development standards: What to verify: Setbacks, height, lot coverage, open space, parking; Why it matters: Often limits yield more than density does
Utilities: What to verify: Electrical, water, sewer and storm drain capacity; Why it matters: Upgrades can add months and major cost
Offsite improvements: What to verify: Street, curb, sidewalk, utility mains, bonds; Why it matters: Can be required before permit or map approval
Fees: What to verify: School, impact, utility connection, plan check; Why it matters: Belong in the pro forma from day one
Site conditions: What to verify: Survey, soils, topography, trees, demolition; Why it matters: Drive foundation, grading and site cost
Title and access: What to verify: Easements, CC&Rs, access rights; Why it matters: Can remove buildable area or block a plan
Exit value: What to verify: Comps, rents, absorption, subdivision path; Why it matters: Confirms the deal works at the end
1. Zoning and Density
Start with what the city will actually allow, not what the listing says. Confirm the base zone, the general plan designation and any specific plan or overlay that changes the rules. Then check whether state law adds capacity on top of local zoning:
State density bonus: affordable units can unlock additional density, concessions and reduced parking.
Transit-oriented upzoning: SB 79 allows higher height and density on qualifying sites near major rail and bus stops in covered cities.
Small-lot and lot-split tools: SB 9 lot splits, ADU rules and small-lot subdivisions can add units or create for-sale lots.
Write the unit count down as a range, from base zoning to the best case with state programs, and underwrite to the number you can defend.
2. Development Standards
Density is a ceiling. Setbacks, height limits, lot coverage, open space, fire access and parking decide how many units physically fit. A quick massing study on the actual lot dimensions is the fastest way to find the real yield before you pay for full design.
3. Utility Capacity
This is the most common blind spot we see. Before closing, find out:
Electrical service: whether the existing service and nearby transformer can carry the new load, and what the utility will require for new meters or a service upgrade. Utility timelines can run longer than the building permit.
Water and sewer: the size and condition of the mains, whether laterals need replacement and whether the agency requires a capacity study.
Storm drain: on-site retention or treatment requirements, which take buildable area and add cost.
4. Offsite Improvements and Bonds
Cities and counties often require street dedications, curb, gutter and sidewalk, utility main extensions or street lighting as a condition of approval. Many require these improvements to be bonded before a permit or final map issues. Ask the public works department what it will require for a project of your size, and carry the cost and the bond in your budget.
A new state law, SB 1014, requires cities to disclose infrastructure requirements within 30 days of receiving a housing application and bars new requirements after the application is submitted. Use that window to lock down offsite scope early.
5. Fees
Fees vary widely by jurisdiction and can be a meaningful share of total project cost. Build a fee schedule for the specific site that includes plan check and permit fees, school fees, development impact fees, park fees and utility connection charges.
Under the Housing Crisis Act (SB 330), a complete preliminary application generally locks in the fees and development standards in effect when it is submitted. Filing one early can protect your pro forma from later fee increases.
6. Site Conditions
Boundary and topographic survey: confirms the lot area your density is based on and the grades you will build on.
Geotechnical report: soil conditions drive foundation design, grading and retaining walls.
Existing structures: demolition scope, hazardous materials testing and any protected trees.
Environmental review: a Phase I report where past uses suggest contamination risk.
7. Title, Easements and Access
Read the preliminary title report line by line. Utility easements, access easements and recorded restrictions can remove buildable area or conflict with a site plan. Confirm legal access for construction and for the finished project.
8. Exit Value
Underwrite the end before you commit to the beginning. Pull sale comps or rent comps for the product you plan to build, confirm the subdivision path if you plan to sell individual units, and check that the exit value supports the total project cost with the margin your lender and investors expect.
When to Bring Us In
We review sites during your due-diligence period, so feasibility, yield, utility requirements and an order-of-magnitude construction budget are in hand before your deposit goes hard. At Mission Sierra in San Gabriel, we found the property, led permitting, secured construction financing, demolished the existing home and built three new residences, so we underwrite sites the way a developer does.
Planning a development?
Ramos Construction Group is a majority women-owned general contractor and developer based in Santa Ana. We provide site feasibility, development and exit analysis, utility coordination, permit expediting and general contracting for ground-up residential, townhome and mixed-use projects across Southern California.
Call (949) 688-3455, text (949) 394-4753 or visit rcgbuild.com to schedule a feasibility consultation.
Sources
California HCD, State Density Bonus Law fact sheet (April 2026): https://www.hcd.ca.gov/sites/default/files/docs/planning-and-community/density-bonus-law.pdf
SCAG, Summary of the Housing Crisis Act of 2019 (SB 330): https://scag.ca.gov/sites/main/files/file-attachments/senate_bill_330_and_senate_bill_8_-_summary_of_housing_crisis_act_of_2019.pdf
The MortgagePoint, Newsom signs six housing bills (Oct. 2026): https://themortgagepoint.com/2026/10/09/newsom-signs-6-bills-to-reduce-construction-costs-expand-housing-options-in-california/
This article is general information, not legal, financial or investment advice. Zoning, entitlement and permitting requirements vary by jurisdiction and change over time; confirm requirements for your site with the local planning and building departments.

