Street work, utility upgrades, bonds and deposits rarely appear in a first pro forma. They can hold up a permit or a final map for months. Here is how to find them early and budget for them.
A developer can close on land, complete design and clear plan check, then sit idle because the city requires a new sewer main, a widened street or a bond the project never budgeted for. Offsite improvements and the security that guarantees them are among the most common reasons a development stalls before construction starts.
None of these costs are hidden on purpose. They are simply discovered late, because no one asked the right questions before the land was bought and the design was drawn.
What Counts as an Offsite Improvement
Offsite improvements are public infrastructure outside your building footprint that the city, county or utility requires as a condition of approval. Common examples:
Street: Street widening, repaving to centerline, new or upgraded street lights, traffic signage and striping
Curb, gutter and sidewalk: New or replaced curb, gutter, sidewalk, driveway approaches and accessible curb ramps
Dedications: Land given to the city for right-of-way, sidewalk or utility easements, which can reduce buildable area
Sewer: Upsized sewer mains, new manholes or capacity studies when the existing line cannot carry the added flow
Water and fire: Water main upgrades, new fire hydrants, fire service connections and flow testing
Storm drain: Drainage improvements and on-site or offsite stormwater capture
Dry utilities: Electrical service extensions, transformers, undergrounding of overhead lines and conduit for telecom
The Bonds and Deposits Behind Them
Subdivision improvement agreements
When a project includes a subdivision map, such as for-sale townhomes or condominiums, the city typically requires the developer to sign an improvement agreement and post security guaranteeing the required improvements will be built. Under California’s Subdivision Map Act, that security commonly includes:
Faithful performance security: at least 50% and up to 100% of the estimated cost of the improvements, guaranteeing the work will be completed.
Labor and materials security: at least 50% and up to 100% of the estimated cost, guaranteeing payment to the contractors and suppliers who build the improvements.
Warranty security: an amount set by the local agency, covering defects for one year after the improvements are completed and accepted.
Security can take the form of surety bonds, cash deposits or letters of credit, depending on the agency. Bonds require underwriting, and sureties look at the developer’s financial strength, so arrange bonding capacity early.
Tax certificates and tax security
Before a final map or parcel map can be filed, the Map Act requires a certificate showing no liens on the property for unpaid taxes or special assessments. For taxes that are a lien but not yet payable, counties can require security, such as a tax bond or cash deposit, before the map records. This step catches developers by surprise because it arrives at the very end of the map process.
Utility deposits and fees
Electric, water and sewer providers often require engineering deposits, design fees and construction advances before they design and build service extensions. Utility design and construction timelines can run longer than plan check, so these requests should go in early.
Development impact and school fees
Cities and counties charge development impact fees for parks, traffic, sewer and other public facilities, and school districts levy developer fees on new residential square footage. School fees are typically paid to the district before the building permit issues. Fee schedules vary widely by jurisdiction and change often, so pull the current schedule for your site during due diligence.
A New Tool for 2027: SB 1014
Starting January 1, 2027, SB 1014 gives housing developers a way to learn infrastructure requirements earlier:
Up-front estimate: when filing a preliminary or development application, an applicant can request a good-faith, nonbinding estimate of required onsite and offsite improvements. The city or county must respond within 30 business days.
Utility requests: applicants can make a similar request to the applicable utility agencies.
Itemized list after approval: within 30 business days of deeming a post-entitlement permit application complete, the agency must provide an itemized list of required improvements, and improvements not on the list are generally barred, subject to specified exceptions.
Use these requests. They turn offsite costs from a late surprise into a number you can put in your pro forma and your loan request.
How to Budget and Sequence Offsite Costs
Before you close: meet with the planning, public works and utility departments. Ask what offsite improvements, dedications and capacity studies similar projects nearby were required to complete.
During due diligence: order a survey, a title review for existing easements and, where sewer or water capacity is in question, a capacity check with the provider.
At application: request the SB 1014 estimate from the city and the utilities, starting in 2027.
In the budget: carry offsite improvements, bond premiums, deposits, tax security and fees as separate line items, with contingency, rather than burying them in soft costs.
In the schedule: sequence utility design, bond posting and tax security so they are complete before you need the permit or the final map, not after.
With your lender: confirm how the construction loan treats bonds, deposits and offsite work. Some of these costs come due before the first draw and must be funded with equity.
Common Mistakes
Assuming the existing street and utilities are adequate. Added units and added flow are exactly what trigger upgrades.
Ignoring dedications. A right-of-way dedication can shrink the lot and cost a unit.
Treating bonds as paperwork. Bonding requires underwriting and collateral and takes time.
Forgetting the tax security at map recording. It arrives late in the process and must be funded in cash or bonded.
Waiting on the utility. Electrical service design is often the longest lead item on a residential project.
How We Help
Ramos Construction Group identifies offsite improvements, utility requirements and fees during feasibility, before you close. We coordinate directly with utility providers, including Southern California Edison and municipal power companies, and we build these costs into a lender-ready construction budget. As developers ourselves, we know what these costs do to cash flow: at Mission Sierra in San Gabriel, we found the property, led permitting, secured construction financing, demolished the existing home and built three new residences.
Planning a development?
Ramos Construction Group is a majority women-owned general contractor and developer based in Santa Ana. We provide site feasibility, development analysis, design coordination, permit expediting, utility coordination and general contracting under one roof, for ground-up residential, townhome and mixed-use projects across Southern California.
Call (949) 688-3455, text (949) 394-4753 or visit rcgbuild.com to schedule a feasibility consultation.
Sources
California Government Code style="white-space:pre-wrap;" data-rte-preserve-empty="true" 66499.3 (improvement security): https://california.public.law/codes/ca_gov't_code_section_66499.3
California Government Code style="white-space:pre-wrap;" data-rte-preserve-empty="true" 66492 (taxes and assessments before map filing): https://california.public.law/codes/government_code_section_66492
Holland & Knight, California’s 2027 Housing Laws: What You Need to Know: https://www.hklaw.com/en/insights/publications/2026/10/californias-2027-housing-laws-what-you-need-to-know
This article is general information, not legal, financial or investment advice. Zoning, entitlement and permitting requirements vary by jurisdiction and change over time; confirm requirements for your site with the local planning and building departments.