Power is one of the longest lead items on any multi-unit project. Here is how to plan electrical service so the utility is ready when your building is.
On a multi-unit project, electrical service is rarely just a line item. A new transformer, a service extension from the street or a meter bank sized for a dozen units can take months of utility engineering, permitting and construction. If the application starts after the building permit issues, power can become the item that holds up your certificate of occupancy.
Developers who plan electrical service at the start of design avoid that delay. Here is what drives the process, how it works with Southern California Edison (SCE) and city-owned utilities, and what to do early.
Start With the Load
Everything the utility designs flows from your project’s electrical load. Your electrical engineer calculates it from the building program, and the result drives service size, transformer capacity and meter configuration. The biggest drivers on a modern residential project are:
Number and size of units. Every unit adds lighting, receptacle, kitchen and laundry load.
All-electric systems. Heat pumps for space and water heating and electric cooking replace gas, so the electrical service carries loads that gas once handled.
EV charging. California’s green building code (CALGreen) requires new multifamily projects to provide EV-ready parking and installed Level 2 chargers for a share of spaces. Those circuits add real capacity to the service.
Common areas and site loads. Corridor and site lighting, elevators, pumps, gates and amenity spaces.
Solar and battery storage. Systems required or chosen under the energy code affect interconnection and service equipment.
California’s 2025 Energy Code took effect January 1, 2026. It expands heat pump baselines for new multifamily buildings and updates solar and battery storage standards for high-rise multifamily. Confirm with your designer which edition applies to your permit application, because it shapes your load.
How the SCE Process Works
SCE publishes an eight-step energization process for new service. Some steps are the utility’s responsibility; others depend on you.
1. Application: What happens: You submit the project request; SCE reviews it for completeness; Who drives it: Developer and engineer
2. Engineering and design: What happens: SCE visits the site, runs engineering studies, designs the service and sets the cost; Who drives it: SCE
3. Customer requirements: What happens: Permits, easements, signed contracts, fees and any third-party approvals; Who drives it: Developer
4. Utility approvals: What happens: SCE files its own permits and easement documents; Who drives it: SCE
5. Site readiness: What happens: Pre-construction meeting and inspection; on most projects, your team builds the trenches, conduit and pads; Who drives it: Developer and contractor
6. Utility readiness: What happens: SCE completes its pre-construction work and inspections; Who drives it: SCE
7. Construction: What happens: SCE installs cable, transformers and equipment, including any outages and traffic control; Who drives it: SCE
8. Energization: What happens: Final inspections, then the service is energized; Who drives it: SCE and city
What the published timelines tell you
SCE reports an average application review of 10 business days, with a maximum of 45. For the work it controls, its energization targets for line extensions and service extensions average 125 business days, roughly six months. Those targets cover only SCE’s own steps. Your permits, easements, contracts, fees and onsite civil work add time on top, which is why the application belongs at the start of design, not after permit.
City-Owned Utilities Work Differently
Not every Southern California site is served by SCE. Cities such as Los Angeles (LADWP), Pasadena (Pasadena Water and Power) and Anaheim (Anaheim Public Utilities) run their own electric utilities, each with its own application process, design standards, fees and timelines. Confirm who serves your site during due diligence, then get that utility’s requirements in front of your design team early.
Design Decisions That Affect Power
Service size and meter configuration
Multi-unit projects typically need a meter for each unit plus a house meter, grouped in a meter room or exterior meter bank. The location must meet the utility’s clearance and access rules and work with the architecture. Moving it after design means redesign.
Transformer location
A new pad-mounted transformer needs space, access for utility trucks, clearances from buildings and openings, and often an easement. On a tight infill lot, that pad can cost you parking, open space or units if it is not planned from the first site plan.
Underground service
Many cities require underground service for new construction, and some require existing overhead lines along the frontage to go underground. Trenching, conduit and vaults are usually the developer’s responsibility and belong in the budget from day one.
Load management
EV charging and all-electric equipment can be paired with load management systems that control peak demand. Your engineer can evaluate whether that keeps the service size, and the transformer, smaller.
Common Mistakes
Applying after the building permit. The utility’s clock does not start until it has a complete application.
Leaving the transformer off the site plan. A late transformer location can force a redesign of parking, landscaping or the building footprint.
Assuming capacity exists. The circuit serving your street may need upgrades to carry your load. Ask early.
Budgeting for the utility’s fee only. Your own trenching, conduit, pads, meter equipment and street restoration are often the larger cost.
Missing easements. Utility easements require signatures and recording, and the utility cannot build without them.
An Early-Planning Checklist
Confirm the serving utility and its available capacity during due diligence.
Run a preliminary load calculation at schematic design, including EV, heat pump and solar assumptions.
Place the transformer and meter room on the first site plan.
Submit the utility application as soon as the load and site plan are stable.
Carry utility costs and time in your budget and schedule, separate from the utility’s own fees.
Coordinate onsite civil work so trenches, conduit and pads are ready for the utility’s inspection.
How We Help
Ramos Construction Group manages utility coordination as part of our preconstruction work, including SCE and municipal power providers. We bring the utility into the schedule during design, build the onsite civil work to its standards and keep the application moving so power is ready when the building is.
Planning a development?
Ramos Construction Group is a majority women-owned general contractor and developer based in Santa Ana. We provide site feasibility, development analysis, design coordination, permit expediting, utility coordination and general contracting under one roof, for ground-up residential, townhome and mixed-use projects across Southern California.
Call (949) 688-3455, text (949) 394-4753 or visit rcgbuild.com to schedule a feasibility consultation.
Sources
Southern California Edison, Overview of the Energization Process and Project Timing: https://sce.com/sites/default/files/custom-files/PDF_Files/Overview-of-the-Energization-Process-and-Project-Timing.pdf
Southern California Edison, Expansions and New Facilities: https://www.sce.com/business/resources/consulting-services/expansions-new-facilities
California Energy Commission, 2025 California Energy Code Fact Sheet: https://www.energy.ca.gov/sites/default/files/2024-09/2025_California_Energy_Code_Fact_Sheet_ada.pdf