The construction contract decides who carries the risk when costs move. Here is how the three common structures compare and when each one fits.
Two contractors can build the same project for the same price and leave a developer in very different positions. The difference is the contract. It decides who absorbs cost increases, how changes are priced, how much of the cost you can see and how much certainty you bring to your lender.
Most construction contracts fall into one of three structures: a fixed bid, a cost-plus contract or a guaranteed maximum price (GMP). Here is how each works.
Fixed Bid (Lump Sum)
Also called a stipulated sum, a fixed bid is a single price for a defined scope. The contractor prices the complete plans, and the developer pays that amount, adjusted only by change orders.
Strength: a known number at signing, which is simple for budgeting and lending.
Weakness: the contractor builds its risk into the price, and you see the total, not the costs behind it.
Watch for: change orders. Any gap or ambiguity in the drawings becomes an extra, and a low bid on incomplete plans often becomes a high final cost.
Best fit: fully designed projects with complete drawings and little uncertainty.
Cost-Plus
Under a cost-plus contract, the developer pays the actual cost of the work plus a fee, either a fixed amount or a percentage of cost.
Strength: full transparency, and work can start before the design is complete.
Weakness: no ceiling. If costs rise, the developer pays for it.
Watch for: a percentage fee, which grows as costs grow. A fixed fee aligns incentives better.
Best fit: projects with real unknowns, such as repairs or renovations where conditions are hidden until work begins.
Lenders are often cautious about an open-ended cost-plus contract, because it leaves the construction cost uncapped.
Guaranteed Maximum Price (GMP)
A GMP contract sets a maximum price for the defined scope. The contractor builds the project and guarantees the cost will not exceed that price. Costs that would push the project over the maximum are the contractor’s responsibility, except for changes approved through a change order.
Strength: a ceiling on construction cost, which protects the developer’s budget and the lender’s underwriting.
Strength: the contractor is accountable for its own estimate. If it misjudges the cost of the defined scope, it absorbs the difference.
Watch for: the scope definition. A GMP is only as strong as the drawings, specifications, allowances and exclusions it is based on.
Best fit: ground-up development where the builder is involved during design and the budget must hold for the lender.
Side-by-Side Comparison
Price certainty: Fixed bid: Set at signing; Cost-plus: None; GMP: Capped at the maximum price
Who carries overruns: Fixed bid: Contractor, within the defined scope; Cost-plus: Developer; GMP: Contractor, within the defined scope
Cost visibility: Fixed bid: Total only; Cost-plus: Full; GMP: Defined by the contract
Design needed to sign: Fixed bid: Complete; Cost-plus: Can start early; GMP: Developed enough to define scope
Change orders: Fixed bid: Every gap becomes one; Cost-plus: Absorbed into cost; GMP: Only for approved scope changes
Lender view: Fixed bid: Generally favorable; Cost-plus: Often cautious; GMP: Generally favorable
Change Orders, Allowances and Contingency
Every contract type uses the same three tools to handle what is not yet known:
Change orders adjust the price and schedule when the scope changes, such as an owner-requested upgrade or a city-required revision. Agree on how they are priced before you sign.
Allowances carry a set budget for items not yet selected, such as finishes and fixtures. If your selection costs more, the contract adjusts.
Contingency covers unknowns within the scope. Know whose contingency it is and what it can be used for.
Why Design-Build and GMP Work Together
A GMP depends on a well-defined scope, and the best way to define scope is to involve the builder while the project is being designed. In a design-build approach, one team is responsible for design and construction, so cost and constructability shape every drawing. By the time the design is developed, the builder knows exactly what it is pricing and can commit to a maximum.
That is the combination we use. Ramos Construction Group offers design-build and GMP contracts. On a GMP, we guarantee the construction price will not go over. If costs exceed it, we absorb the overage, unless the scope changes through an approved change order.
How to Choose
Is the design complete? If yes, a fixed bid or GMP can work. If not, consider design-build leading to a GMP.
How much uncertainty is in the scope? Hidden conditions favor cost-plus with a fixed fee; defined new construction favors a GMP.
What does your lender need? A capped construction cost usually strengthens the loan package.
Do you trust the scope documents? Whatever the contract, the drawings, specifications, allowances and exclusions decide what you are actually buying.
Planning a development?
Ramos Construction Group is a majority women-owned general contractor and developer based in Santa Ana. We provide site feasibility, development analysis, design coordination, permit expediting, utility coordination and general contracting under one roof, for ground-up residential, townhome and mixed-use projects across Southern California.
Call (949) 688-3455, text (949) 394-4753 or visit rcgbuild.com to schedule a feasibility consultation.
This article is general information, not legal, financial or investment advice. Zoning, entitlement and permitting requirements vary by jurisdiction and change over time; confirm requirements for your site with the local planning and building departments.