A construction loan is approved on the strength of your budget, your schedule and your builder. Here is how to put together a package a lender can say yes to.
A construction lender is underwriting two things: whether the project can be built for the money in the budget, and whether the finished asset will be worth more than the loan. Every document in your package should answer one of those questions clearly.
Developers who treat the budget as a formality pay for it in delays, re-underwriting and smaller loans. Developers who bring a complete, defensible budget and schedule move through review faster and negotiate from a stronger position.
Start With Total Project Cost
Lenders size and approve loans against total project cost, so every dollar needs a place in the budget. The cleanest way to present it is in two parts:
Equity into the deal: the cash you have actually injected, such as the land purchase, design, engineering, entitlement and permit costs you have paid.
Cost of construction: the remaining hard and soft costs to build and complete the project.
Total project cost is equity into the deal plus the cost of construction. Interest payments on an acquisition or land loan are not equity. Lenders count cash that went into the project, and presenting interest as equity undermines the credibility of the whole package.
Hard Costs and Soft Costs
Hard costs: Site work, foundations, framing, roofing, mechanical, electrical and plumbing, finishes, utilities and offsite improvements: everything physically built
Soft costs: Architecture and engineering, permits and fees, school and impact fees, insurance, legal, loan fees, interest reserve, property taxes during construction
Contingency: A reserve for unknowns, carried separately for hard and soft costs
Lenders look hardest at the hard cost budget, because it is where projects most often run over. Each trade should be priced from the plans, with allowances, exclusions and assumptions stated.
What Makes a Budget Credible
Priced from real drawings
A budget built from a permitted or near-permitted plan set carries far more weight than a cost-per-square-foot estimate. If the plans are not final, show which design stage the budget reflects.
Organized by trade
Lenders and their inspectors review budgets line by line. Grouping costs by trade, from general requirements through site work, structure, systems and finishes, makes the budget easy to review and easy to track during construction.
Allowances and assumptions stated
Finish selections that are not final should appear as allowances with a clear basis. Exclusions, such as items bid directly by the owner, should be listed so the lender knows they are carried elsewhere in the project cost.
Fees and offsite costs included
Permit, school and impact fees, utility costs and offsite improvements are frequent sources of surprises. A budget that shows them, even as estimates, signals that the developer has done the work.
Contingency that matches the risk
A new ground-up project on a clean site carries different risk than an adaptive reuse of an older building. Size contingency to the project, and be ready to explain how you arrived at it.
The Schedule of Values and the Draw Process
Once the loan closes, the budget becomes the schedule of values, the line-item breakdown that every draw request is measured against. A typical draw works like this:
The contractor submits a pay application showing the percentage complete for each line of the schedule of values.
The lender’s inspector visits the site to confirm the work in place matches what is being billed.
The lender reviews supporting documents, such as invoices and lien releases, according to the loan terms.
Funds are released for the approved amount.
A schedule of values that matches how the work is actually built makes every draw faster. One that lumps trades together or front-loads costs creates friction with the inspector every month.
Loan-to-Cost and Loan-to-Value
Loan-to-cost (LTC): the loan amount divided by total project cost. It shows how much of the project the lender is funding and how much the developer is contributing.
Loan-to-value (LTV): the loan amount divided by the appraised value of the completed project. It shows the lender’s cushion if the project has to be sold.
Lenders set limits on both, and the lower result usually controls the loan amount. Present both clearly, with the value supported by an appraisal or credible comparable sales and rents.
The Schedule
The construction schedule tells the lender how long its money is out and how much interest the project will carry. A loan-ready schedule shows the major phases, the critical path, long-lead items and utility energization, and it ties to the interest reserve in the budget. An unrealistically short schedule is as much of a red flag as an inflated budget.
The Builder Is Part of the Underwriting
Lenders evaluate the contractor as closely as the budget: license, insurance, experience with similar projects, financial capacity and the construction contract itself. A guaranteed maximum price (GMP) contract strengthens the package because it caps the construction cost the lender is underwriting. Overages become the contractor’s responsibility, except for changes approved through a change order.
A Loan Package Checklist
Total project cost summary showing equity into the deal, cost of construction, LTC and value.
Construction budget by trade, with allowances, exclusions and contingency.
Construction schedule with phases, critical path and completion date.
Plans, permits and entitlement status.
Construction contract and contractor qualifications.
Sources and uses of funds, and evidence of equity already invested.
How We Help
Ramos Construction Group prepares lender-ready construction budgets and total project cost summaries, including costs to date, remaining costs, loan-to-cost and value. We also build on our own projects: at Mission Sierra in San Gabriel, we found the property, led the permitting, secured the construction financing and built three new residences. We know what lenders ask for because we answer those questions ourselves.
Planning a development?
Ramos Construction Group is a majority women-owned general contractor and developer based in Santa Ana. We provide site feasibility, development analysis, design coordination, permit expediting, utility coordination and general contracting under one roof, for ground-up residential, townhome and mixed-use projects across Southern California.
Call (949) 688-3455, text (949) 394-4753 or visit rcgbuild.com to schedule a feasibility consultation.
This article is general information, not legal, financial or investment advice. Zoning, entitlement and permitting requirements vary by jurisdiction and change over time; confirm requirements for your site with the local planning and building departments.